WEEK FIVE: Welding Completed, Floor Framed/Insulated & Openings Flashed
The welding is complete and the steel sheeting on the underbelly of the trailer is now one continuous piece. All 2x3 floor framing is...
WEEK FOUR: Floor Framing Begins
It's been a busy week but slight progress was made: a pseudo walking surface! All of the rusted carriage bolts are removed from the frame...
WEEK THREE: Welding Begins & J-Rail Removal
The metal work is on its way to completion and most of the rusted carriage bolts have been removed from the frame using bolt cutters....
WEEK TWO: Demo, Frame Inspection & Envelope Repairs
This week entailed bathroom demo, removal of the remaining floor and taking down the headliner. Holes in the aluminum siding were patched...
WEEK ONE : Major Demo & Questionable Regrets
When I bought this camper I knew it needed extensive work. I wanted the project. What I didn't know is that the entire floor frame was...
THE BEGINNING: New Project. | Challenge Accepted.
Let me start by saying how fearful/thrilled I am. Tiny homes and small space living is something I find super interesting. While this is...