WEEK SIXTEEN: Ceiling Panel Prep & Install
Work Clean-Up and Ceiling Prep Lessons learned: don't use rough sawn lumber for wall framing. The 1x8 boards I used at the exterior...
WEEK FIFTEEN: Wall/Roof Construction, Interior Framing & Shower Pan
Interior Cabinets The left side of the bedroom partition is installed; this gives a lot of rigidity to the exterior wall and provides a...
WEEK FOURTEEN: Bedroom Wall Framing, Camper Storage & New Router
I've been anxiously waiting to get to this point and now that I'm here it's a bit unnerving to take the dive. The partition that will...
WEEK THIRTEEN: Work Space Reno, New Hardware & Shower Progress
This week was largely split up between traveling for work and heading out for the last long weekend of the summer, but before I left I...