
WEEK EIGHT: Roof Vents Replaced, Roof Framing Completed & End Wall Framing Begun
In preparation for the application of a new rubber roof coating roof vents replaced and roof framing substantially finished. I chose to go with Liquid Roof’s EPDM RV roof repair which is designed to be applied over existing coatings/sealants since mine is currently built up a bit and cracked due to the fact that the product likely wasn’t designed for extensive movement. After digging down through multiple layers of roof sealers (a seemingly tar-based coating and additional UV

WEEK SEVEN: Side Wall Framing Completed & Roof Framing Begins
The left wall is in place! Using 2x4's as support, a few family members and a handy hammer I was able to slide the skin around the wall panel. Add a lot of discomfort/frustration to that and it was that simple. The siding was definitely less forgiving the second time around but it did fit. Both side walls are now constructed and I've begun roof construction (about half of the rafters are installed). The red stripe accent on the aluminum siding is proving resistant. I'm now st

WEEK SIX: Side Wall Construction Begins
The door/windows, trim, J-rail and siding has been removed on right side in order to begin construction on the first side wall. All screws are rusted or stripped so the gutters were pried off, resulting in them being slightly less salvageable than I hoped. Using the siding as a template I've stenciled the wall shape and assembled the framing while keeping in mind the floor plan I've created to give proper support within the wall (for cabinets, walls, etc). I've taken directio

WEEK FIVE: Welding Completed, Floor Framed/Insulated & Openings Flashed
The welding is complete and the steel sheeting on the underbelly of the trailer is now one continuous piece. All 2x3 floor framing is assembled and fastened, insulation installed and subfloor laid. I scored some discounted batt insulation at Home Depot (the lack of plastic packaging apparently makes it really hard to sell) and was able to do the whole floor for $5. I chose 3/4" DryPly marine grade plywood for the subfloor and all floor penetrations are flashed; exposed corner

WEEK FOUR: Floor Framing Begins
It's been a busy week but slight progress was made: a pseudo walking surface! All of the rusted carriage bolts are removed from the frame and the last bits of old rotted floor framing pulled out. I drew up a plan for the new framing layout as guide and for future reference. I'm beginning to lay out the 2x3 floor joists and most are cut to fit/drilled according to the existing bolt locations. There is some final welding to be done before fastening but the pieces are prepared.