WEEK THIRTY-FIVE: Bathroom Build & More Electrical

Bathroom Build

Wall lifted in place. Shower pan lip hooks over the door opening which adds significant strength. Tank 'floor' complete, new toilet flange threaded in and toilet installed. Floor fastened downwards into wall framing and also fastened horizontally at the exterior wall. Light switch in place.

More Electrical

Holes cut in ceiling panels for recessed light fixtures. Main cabin outlets/light switches installed. Main electrical panel in place. Sound system installation begun but not yet complete.